TO WHOM IT MAY CONCERN
FROM: Stephanie Barrett
RE: Route 104 Fairfax – St. Albans Town Repaving Project
DATE: 5/28/2010
The following is the schedule of the construction to take place on Route 104 for the week starting June 14, 2010.
Monday:
Guardrail work at the intersection of Route 104 and Access Road to Interstate 89.
Monday & Tuesday:
Weather permitting, line striping to begin throughout the project limits.
Monday thru Friday:
Weather permitting, continued driveway tie-ins throughout the project limits.
Please note traffic control will be present. We ask motorists to use extreme caution while traveling through the zone. The safety of the workers along with the motorists is of the utmost importance.
The Public Relations telephone number for the public to call with any questions or concerns is 802-862-6085.