Henry Raymond

Fairfax News => Current News & Events => Topic started by: Henry on June 11, 2010, 01:11:56 PM

Title: Route 104 Fairfax - St. Albans Town Repaving Project 5/28/2010
Post by: Henry on June 11, 2010, 01:11:56 PM

TO WHOM IT MAY CONCERN      

FROM:   Stephanie Barrett

RE:      Route 104 Fairfax – St. Albans Town Repaving Project

DATE:      5/28/2010




The following is the schedule of the construction to take place on Route 104 for the week starting June 14, 2010.


   
Monday:
Guardrail work at the intersection of  Route 104 and Access Road to Interstate 89.

Monday & Tuesday:
Weather permitting, line striping to begin throughout the project limits. 

Monday thru Friday:
Weather permitting, continued driveway tie-ins throughout the project limits.

   

Please note traffic control will be present.  We ask motorists to use extreme caution while traveling through the zone.  The safety of the workers along with the motorists is of the utmost importance.

The Public Relations telephone number for the public to call with any questions or concerns is 802-862-6085.