Post by: Henry on August 27, 2010, 09:29:41 AM
FROM:   Stephanie Barrett

RE:      Route 128 Westford – Fairfax Repaving Project

DATE:      8/26/2010



The following is the schedule of the construction to take place on Route 128 for the week starting August 30, 2010.


   Monday thru Friday:
Weather permitting, final paving to begin starting in Westford at the intersection of Osgood Hill Road and proceeding north.

Continued ditch work from the “greens” to the northern end of the project in Fairfax.



Please note traffic control will be present.  We ask motorists to use extreme caution while traveling through the zone.  The safety of the workers along with the motorists is of the utmost importance.