Welcome, %1$s. Please login or register.
November 22, 2024, 10:06:01 PM

 
Posts that, in my personal judgement, create too much conflict in the community, may be deleted - If members repost the same topic, they may be banned from future posts - Even though I have disabled the Registration, send me an email at:  vtgrandpa@yahoo.com if you want to register and I will do that for you
Posts: 46173 Topics: 17681 Members: 517
Newest Member: Christy25
*
+  Henry Raymond
|-+  Fairfax News
| |-+  Current News & Events
| | |-+  Repaving Project Update For Rte 128 Starting July 12, 2010
« previous next »
: [1]
: Repaving Project Update For Rte 128 Starting July 12, 2010  ( 3362 )
Henry
Administrator
Hero Member
*****
: 15235



« : July 09, 2010, 07:57:39 AM »

TO WHOM IT MAY CONCERN      

FROM:   Stephanie Barrett

RE:      Route 128 Westford – Fairfax Repaving Project

DATE:      7/2/2010



The following is the schedule of the construction to take place on Route 128 for the week starting July 12, 2010.


   
Monday & Tuesday:
Continued ditch work throughout the project limits.

   Wednesday thru Friday:
Reclaiming to begin in Westford Village and proceeding to the intersection of Routes 128 & 104.

Please note traffic control will be present.  We ask motorists to use extreme caution while traveling through the zone.  The safety of the workers along with the motorists is of the utmost importance.

The Public Relations telephone number for the public to call with any questions or concerns is 802-862-6085.



Henry Raymond
: [1]  
« previous next »
:  

Powered by MySQL Powered by PHP SMF 2.0.18 | SMF © 2021, Simple Machines Valid XHTML 1.0! Valid CSS!