Welcome, %1$s. Please login or register.
November 25, 2024, 12:24:50 AM

 
Posts that, in my personal judgement, create too much conflict in the community, may be deleted - If members repost the same topic, they may be banned from future posts - Even though I have disabled the Registration, send me an email at:  vtgrandpa@yahoo.com if you want to register and I will do that for you
Posts: 46173 Topics: 17681 Members: 517
Newest Member: Christy25
*
+  Henry Raymond
|-+  Fairfax News
| |-+  Current News & Events
| | |-+  Gee!! They Must Be Getting Close To Finished On Route 128
« previous next »
: [1]
: Gee!! They Must Be Getting Close To Finished On Route 128  ( 2583 )
Henry
Administrator
Hero Member
*****
: 15235



« : October 22, 2010, 07:51:06 AM »

TO WHOM IT MAY CONCERN      

FROM:   Stephanie Barrett

RE:      Route 128 Westford – Fairfax Repaving Project

DATE:      10/15/2010

The following is the schedule of the construction to take place on Route 128 for the week starting October 25, 2010.

   Monday thru Friday:
Weather permitting, final driveway tie-ins throughout the project limits.

Please note traffic control will be present.  We ask motorists to use extreme caution while traveling through the zone.  The safety of the workers along with the motorists is of the utmost importance.

The Public Relations telephone number for the public to call with any questions or concerns is 802-862-6085.



Henry Raymond
Mike Raburn
Hero Member
*****
: 2565



« #1 : October 23, 2010, 12:01:42 AM »

I JUST finished my work on the Palmer - Wasilla highway 10-22-2010.
Google "Evergreen and Ellen street, Palmer Alaska".

I am done with medians, striping, signage, stop lights, and highway luminaries.

Give "traffic control" break, please.

They are making your travel safer.

I have had the Alaska Dept of Transportation all over my skinny buttocks for 1 month to complete. IT IS DONE.

: [1]  
« previous next »
:  

Powered by MySQL Powered by PHP SMF 2.0.18 | SMF © 2021, Simple Machines Valid XHTML 1.0! Valid CSS!