TO WHOM IT MAY CONCERN
FROM: Stephanie Barrett
RE: Route 128 Westford – Fairfax Repaving Project
DATE: 8/20/2010
The following is the schedule of the construction to take place on Route 128 for the week starting August 23, 2010.
Monday thru Friday:
Continued ditch work throughout the project limits.
Monday:
Final culvert work with Route 128 remaining closed to thru traffic.
TUESDAY:
ROUTE 128 WILL BE OPENED TO THRU TRAFFIC.
Please note traffic control will be present. We ask motorists to use extreme caution while traveling through the zone. The safety of the workers along with the motorists is of the utmost importance.
The Public Relations telephone number for the public to call with any questions or concerns is 802-862-6085.