A Proposal for a 

   New Town Office

 

 

Article 3      Shall the registered voters of the

                    Town of Fairfax authorize the

                    Fairfax Selectboard to secure a

                    20-year bond for the sum of, not

                    to exceed, $1,300,000.00 to purchase

                land, design/construct a new Town

                Office Building?  Total interest

                payment will be approximately

                $450,000.00. 

 

 

 

 

 

1.  Article 3

 

So, Article 3 asks to borrow an amount

not to exceed $1.3 Million

 

The estimated interest to pay back $1.3

Million over 20 years is $450,000.   So the

total estimated cost is $1.75 million.

 

The land and design portion ($200,000) would be paid back over 5 years.  The construction portion ($1,100,000) would be paid back over 20 years

 

Cost projections are based on an interest rate

of 3.24% quoted by the Vermont Bond Bank.

This percentage is subject to change. Lower

cost financing will be sought.

 

 

 

 

 

 

 

1. Article 3 (continued)

 

The figures showing the increase on local tax are based on the total amount of $1,750,000.,

not just on the $1,300,000.

 

To remind you, the estimated tax on a

property in Fairfax would be:

 

                           First 5 yrs      Years 6-20

     Property        Average          Average

Assessed Value     Cost                 Cost

 

    $100,000          $29.45            $20.04

      200,000            58.90              40.08

      300,000            88.35              60.12

      400,000          117.80              80.16

      500,000          147.25            100.20

 

 

 

 

2.  History

 

a.    1942 Agreement - School to provide

     space for Clerk, Treasurer and Vault

 

b.  Town Office in School

 

c.   1990’s? Town Office moves to

      current school-owned building

 

d.   2007 Engineering Study identifies

      $123,000 worth of needed repairs

 

e.   2008 Town agrees to 20 year lease,

      Town responsible for all costs

 

f.    2010  major water problems in

      the basement

 

g.   2011 Voters reject 9.9 acres for

      $250,000 by margin of 416 to 397

 

h.   2011 Town Office Committee formed

 

 

 

3.  Committee decided it needed to:

 

a.  Understand why the vote failed

 

b.   Study the needs

 

c.   Estimate the cost

 

d.  Analyze the options

 

e.   Involve and educate the public

 

f.   Make recommendations to the

     Selectboard

 

 

 

 

 

 

 

 

 

 

4.  Why did the vote fail? The Voters told us:

 

a.   The need was not clear

 

b.   9.9 acres seemed like too much land

 

c.   Other options needed to be considered

 

d.   The total cost of the project needed to

       be determined

 

 

 

 

 

 

 

 

 

 

 

 

5.  The Need

 

a     Major repairs in the existing office

 

b.    More vault space

 

c.    More and larger office and

       storage space

 

d.    Larger conference room

 

e.    More parking

 

 

 

 

 

 

 

 

 

 

6.  The Needs were quantified

 

a.   Each department was surveyed

 

b.   Current space is approximately 2500

       square feet

 

c.    Preliminary survey showed the

       future need for 5760 square feet

 

d.   The vault would more than double –

       recording stored in the vault has

       doubled since 1998

 

e.    Conference room for 50 people was

       included

 

f.    40+ parking spaces were included

       – we currently have 8 spaces and

       8 employees

 

 

 

Office Space Comparison (Sq. Ft.)

 

                                Current                       Proposed              % Increase

Clerk/Treas.              213                                       391                   84

 

Research                   225                   486                          116

 

Vault                   165                   372                          125

 

Listers                   300                   373                   24

 

Sm. Conf.                    187                   294                   57

 

Utility Dept.                   106                   144                   36

 

SB Assist.                   115                      132                   15

 

Zoning                   232                   404                   74

 

Board Rm.                   None                   778                   ---

 

Town Mgr.                   None                   132                   ---

 

Recreation                   None                   100                   ---

        Subtotal                   1543                   3606                        133

                  

Other                   957                   2157                        125

   (Closets

   Hallways

   Stairs

   Display

   Toilets

   Technology

   Kitchen

   Storage

   Mechanicals)

 

Total                   2500                   5760                        130  

 

 

 

     7.  A professional Estimator

                       Dog River Associates

                         Northfield, Vermont

 

               a.  They gave us their estimate for a

                    5760 square foot building

 

               b.  It is a seven page estimate and

                    probably contains some elements

                    we might not need – but we have

                    used their estimate as the basis for

                    Article 3.

 

               c.   Until we hire a professional to do

                     a comprehensive design based

                     on a complete and thorough

                     analysis, we have agreed to base

                     our cost proposal on the data we

                     collected so far.     

 

 

8  Findings

 

We presented our findings to the Community and solicited input

 

a.    September - Five options presented –

     these three were eliminated

 

1.                    Pomichter property on Butler Street

 

2.                    Boissoneault property across from

     Country Pantry

 

3.                    The Current Town Office

a.                    The School would not sell or

     perpetually lease it to the Town

b.  There is inadequate room for

     the needed expansion

c.  The cost was comparable to

    “new”

 

 

 

                          September

                      Preliminary Cost Estimates ($000)

 

    ITEM                       Option 1         Option 2           Option 3           Option 4         Option 5

                                   (White House)          (Young)               (Pomichter)         (Boissoneault)       (Langelier)

 

      Acres                               None                 2 +/-              4.4                     2.5                    2 +/-

 

Land                                     0                   150                   148                    225                210

 

Road Const.                         0                     20                     20                      10                  10

 

Parking Const.                   40                    40                     40                      40                  40                                                                                                                                                                                                 

Site Prep.                            50                    50                     50                       50                  50

 

Bld. Design                         50                    50                     50                       50                  50

 

Bldg Const.                       450                  864                    864                    864                864

 

Bldg Repair                      300                      0                        0                         0                   0

 

Bldg Renovat.                   200                      0                        0                         0                   0

 

Sewer and Water               10                               40                       20                       40                 20

 

Permitting                            5                                 10                         5                       10                 10

 

Temp. Quarters                 50                                 0                         0                         0                   0

 

Moving                                20                    10                        10                      10                 10

 

 

TOTAL                           1175                 1234                    1207                    1299            1264

 

 

Town Office Preferences

 

White House    Young     Pomichter     Boissoneault    Langelier

 

            5            2            3            4            1

            5            4            2            3            1

            3            1            4            5            2

            5            2            1            4            3

            5            1            4            2            1

            5            1            3            4            2

            5            3            4            1            2

            5            3            4            2            1

            5            2            4            3            1

            5            2            3            4            1

            5            1            3            4            2

            5            1            4            3            2

            3            3            3            2            1

            5            3            4            2            1

            5            3            4            2            1

            5            1            2            4            3

            5            4            3            2            1

            1            2            2            2            2

            5            1            4            3            2

            5            1            4            2            3    

            5            3            4            1            2    

            5            1            4            2            3    

            5            2            4            3            1

            5            1            2            4            3    

            5            2            1            3            4

            5            1            3            4            2

         122               51                 83                     75                  48       

Note:  The lowest numbers are the most preferred                                                                                 

               

 

     8.  Findings  (continued)

 

b.    December -  Two options (Young and

      Langelier) were presented, with costs

      and Pros and Cons – The community  

      was split fairly evenly

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                         December

      Preliminary Cost Estimates ($000)

 

 

    ITEM                               Option 1                               Option 2

                                                                                  ( Young)                                      (Langelier)

 

Acres                                           2 +/-                                         2+

 

Land                                     $ 150                                      $  210

 

Road Const.                              20                                            20

 

Parking Const.                         40                                            40                                                                                                                                                                                                 

Site Prep.                                  50                                            50

 

Bld. Design                               50                                            50

 

Bldg Const.                             864                                          864

 

Sewer and Water                     40                                            30

 

Permitting                                10                                            10

 

Moving                                     10                                            10

 

Landowner Contribution      -22

                                                                     ____                                          ____

 

 

TOTAL                            1212                                        1284

 

 

 

                                                      December

Pros and Cons

Langelier Parcel

         Pros:

              sewer and water lines nearby

              right of first refusal on additional land

              visible from Main Street

         Cons:

              price per acre ($210,000 for 2 acres)

              outside the current Growth Center (potentially higher

                    loan interest rate)

              no sidewalks on Buck Hollow Road

              further from the existing sidewalk network

              busy road with high speed traffic

              bad intersection at bottom of Buck Hollow Road

Young Parcel

          Pros:

              lower purchase price ($150,000 for approx. 2 acres)

              within the Growth Center (possible preferential financing)

              easy walking distance from village

              sidewalks to the boundary

              sewer and water lines nearby

              right of first refusal on additional land

              current buildings to removed by the Youngs

              adjacent to Fire Dept. and potentially the Rescue Squad

        Cons: 

              access road (Rich Street) to be taken over by the Town

                  (must meet Town Standards or be upgraded)            

              not visible from Main Street 

              possible contamination from prior “shop,” but

              is being addressed at no cost to the Town

 

 

 

 

8.   Findings (continued)

 

c.   February -  After the Selectboard

      decided its preference was for the

      Young parcel, a third Community

      Discussion took place.

 

1.                  Some members of the audience

      were dissatisfied with the site

      chosen

 

2.                  Some members of the  audience

      felt the cost was too high

 

 

 

 

 

 

 

 

 

 

9.    So lets review the Cost Estimate

      (the not-to-exceed $1,300,000)

 

         Cost Element                                      Amount ($000)

              Land                                                            150 

              Road and parking                                        60

              Sewer and Water                                         40

              Site Work                                                     50

              Permitting                                                    10

              Moving                                                         10

              Design                                                           50

              Construction  Estimate

                      General conditions                            146

                      Site Work                                       Covered

                      Permitting                                      Covered

                      Concrete                                               88

                      Metals                                                     1

                      Framing                                                62

                      Siding and ext. Trim                           29

                      Interior and General Carpentry        17

                      Roofing and Insulation                       45

                      Doors and Windows                            41

                      Finishing                                               94

                      Vault                                                     53

                      HVAC and Plumbing                        103

                      Electrical                                              76

                      Design                                             Covered

                      Overhead and Profit                           70

                      Contingency   (5%)                             44

 

                                Total                                         1239

9.   Cost Estimate  (continued)

 

In our February Community Discussion

members of the audience were concerned

that the estimated cost of construction was

too high.

 

If we look at the construction portion of the

estimate on the previous foil, it totals

$869,000.

 

If you divide this number by 5760 square

feet, you come up with approximately

$151 per square foot.  

 

 

 

 

 

 

 

 

 

 

10.    Summary

 

The need is real, and pressing. If we are

forced to spend money on the current

office, and then leave, we will have spent

more money than needed

 

The options were studied carefully

 

The community participated in the process

 

We understand that the project is expensive

and that times are tough for many people,

but the longer we wait the more likely it is

that the project will become more expensive.

 

If we have a crisis and no place to go, we could

be in trouble.     

 

Please consider voting “Yes” on Article 3